Northbound Route 29 (Lee Highway) will have single-lane closures between White Post Road and Paddington Lane, weather permitting, from 10 p.m. Sunday, July 31 to 5 a.m. Monday, Aug. 1 to implement a traffic shift, according to the Virginia Department of Transportation.
During that time, the northbound Route 29 lanes between White Post Road and Paddington Lane will be shifted to the left until this fall.
The shift is part of the project to rehabilitate the northbound Route 29 (Lee Highway) bridge over Cub Run to improve driver and pedestrian safety and extend the overall life of the bridge. The improvements include:
• Replacing the concrete deck and bridge rails
• Installing steel beams
• Adding a walkway with barrier and connecting the walkway to the existing sidewalk just north of the bridge
• Rebuilding the concrete pedestals
• Replacing the bridge bearings
• Repairing cracks
The project is scheduled for completion in spring 2023.