Road work on Vint Hill Road and Va. 28 will create lane closures and detours in the area throughout the summer. The road closures will be part of road improvements to widen Va. 28 between Linton Hall Road and Fitzwater Drive. The realignment of Vint Hill Road is part of the project.
Vint Hill Road:
The first weekend closure of Vint Hill Road at Va. 28 was between 10 p.m. on Friday, June 5, and 4 a.m. on Monday, June 8, according to the Prince William County Department of Transportation
Vint Hill Road at Va. 28 will be closed again between 10 p.m. on Fridays and 4 a.m. on Mondays during the weekends of July 17 through Aug. 16.
The detour around the work on Vint Hill Road will be Schaeffer Lane to Determination Road.
Va. 28:
Va. 28, at Vint Hill Road, will be closed on weekend nights only for three weekends in June and one weekend in July.
The weekend closures on Va. 28 are:
· June 12 – 14
· June19 – 21
· June 26 – June 28
· July 10 – July 12
The closures are only on those weekend nights at the following times:
· 10 p.m. Friday through 5 a.m. Saturday
· 10 p.m. Saturday through 5 a.m. Sunday
· 10 p.m. Sunday through 4 a.m. Monday
Traffic will be detoured to Kettle Run Road to get around the work on Va. 28.
The lane closure schedule is tentative to the construction schedule, progress and weather.
More information about the Route 28 project can be found at http://www.pwcgov.org/transportation.
Copy and paste the code below on your site to link to the article.
<a href="http://www.bullrunnow.com/news/article/03966">Road work on Vint Hill and VA Rt. 28 during weekends this summer</a>